Falconbridge Mines

Northern Quebec, Canada

Falconbridge Mines
  • Nickel / Copper mine facilities
  • Size: 12 pre-assembled modules
  • Tons of Steel: 6,000 tons
  • Engineer & General Contractor: Bechtel Canada
  • Project total: $486 million
  • Nickel and copper mine
  • 12 preassembled modules were built for the mine's concentrator and the power plant
  • Concentrator handles 800,000 metric tons of ore annually
  • 130,000 metric tons of high-grade nickel/copper concentrate is produced > Modules were barged 2,800 nautical miles to the mine site
  • The mine is roughly 250 miles south of the Arctic Circle

The stakes were high for the development of Falconbridge's Raglan mine in northern Quebec. The property was proven to contain one of the best undeveloped nickel-copper deposits in the world, but the harsh environment, and remote location of the site presented an incredible range of physical challenges and logistical issues that would require a $400 million investment and many innovative measures to overcome.

After solving regulatory, environmental and native rights issues, Falconbridge turned to Bechtel for management of mine's development. As one of the few engineering, procurement and construction (EPC) companies in the world that could handle such a complex development, Bechtel was a clear choice for building a high capacity mining operation that would work eight months per year, within 250 miles of the Arctic Circle.

The biggest obstacle that Bechtel faced was that construction could only occur at the site within a short four-month window each year. To work around this, the site was prepared in stages of intense construction over three northern summers, with the majority of the facilities being preassembled as modules in the south, then barged up and pieced together.

Completed in 1998 (three months ahead of the original schedule), the concentrator at the mine annually turns 800,000 tonnes of excavated ore into 130,000 tones of high-grade nickel/copper concentrate. The concentrate is then trucked 60 miles to port facilities (constructed as part of the project), where ships haul the concentrate south to Quebec City, and trains take it on to smelters in central Ontario.

Every year the mine produces approximately 21,000 metric tons of nickel, 5,000 metric tons of copper, 200 metric tons of cobalt, plus varying levels of platinum metals.

Timing is Everything

Bechtel hired Supermetal for the fabrication and erection of the concentrator and power plant facilities. Because of the short construction window at the northern mine site, Bechtel created an elaborate plan for developing the facilities with pre-assembled modules. The steel for the twelve modules, was fabricated at our St. Romuald plant near Quebec City, and immediately taken to a nearby dock. Supermetal assembled the ten to twelve-story high modules in a staging area that was roughly the size of two city blocks.

modules pré-assemblés

Continued exploration of the property, and upgrades to the facilities will allow Falconbridge to eventually increase annual production of nickel to above 30,000 metric tons.

Fabrication and erection schedules on this project were extremely rigorous, and all parties involved in the development were required to work with perfect timing. Ice in the receiving harbor up north meant that the ships could not leave too early, while a short window for final assembly at the site meant that no piece of the project could be delivered even a little late.

Big Rewards from Hard Work

Completed on time, and perfectly assembled for shipping, the modules - each weighing several hundred tonnes - were inched from the staging area onto waiting barges. Three ships, each took four of the huge modules on its decks and began the 2,600 nautical miles journey to the mine's remote northern location.

The modules were put ashore onto a dock built specially for the project and road hauled to the mine site, where Supermetal completed the intricate assembly process.

péniches de transport

The pre-assembled modules were loaded on three huge barges, and shipped 2,600 nautical miles to the mine's remote northern location.

Supermetal worked with absolute precision to complete the pre-assembly, and final assembly before the required dates. The first shipload of nickel/copper concentrate left the Deception Bay harbor in March 1998 - three months ahead of the originally scheduled sailing.

Photo Gallery

falconbridgeLarge2 falconbridgeLarge3 falconbridgeLarge4
  • Company tour
  • Legal notices
  • Download
  • Employee / client access
  • Site map
  • FAQ
© 2009-2010 Supermétal Structures All rights reserved
Supermétal Structures
1955, 5e rue
St. Romuald, Quebec
Canada G6W 5M6

Telephone: (418) 834-1955
Email: supermetal@supermetal.com
Website: www.supermetal.com

Printed on: Saturday, July 31, 2010